G10 Blog 4
Blog 4 During the period of November 11 to November 25 the team worked mostly on generating a production plan. This involved sourcing buyout materials, tabulating a lead time for ordered parts, outlining the manufacturing process, and exploring potential places to execute manufacturing processes. Table 1 shown below shows the compilation of the research and includes the cost of the items including tax, its purpose, and the vendor the team has identified. Table 1: Items needed for Manufacturing Process Table 2 shown below shows the manufacturing processes the team has identified that will be needed to build the prototype. For each process, the expected time duration has also been identified and as a whole the manufacturing process is expected to take 64 days from start to finish. Table 2: Estimated Time for Each Manufacturing Process Other details in the manufacturing process have also been decided by G10 which includ...